What Happens After You Sign a Building Contract? A Guide to Building Your New Home

What happens after signing a building contract in Australia? Follow the stages from approvals and foundations to progress payments, practical completion and handover.

An unbranded building contract on a modern desk, ready for review before home construction

You’ve chosen your builder, agreed on a home design and signed the building contract. But what actually happens next? Understanding the construction process can help you know what to expect, what questions to ask and how to stay informed throughout your build.

What Happens After You Sign a Building Contract?

Signing a building contract is an important milestone, but it doesn’t necessarily mean construction will begin immediately.

Depending on your project, the builder may still need to finalise plans, engineering, approvals, selections and other pre-construction requirements.

Once construction begins, the home will generally progress through site preparation, foundations, framing, external construction, internal services, fit-out and completion.

Along the way, there will be inspections, progress payments and decisions that may affect the cost or timeframe.

The exact sequence will depend on the builder, the design and the construction method.

The important thing is understanding what should happen at each stage, what you’re being asked to approve and when important work needs to be checked.

Let’s walk through the process.

What Should You Do Immediately After Signing?

A few practical checks can help you understand where your project stands:

  • Confirm your documents. Keep the signed contract and check that the agreed plans, specifications and selections are properly recorded.
  • Find out what’s outstanding. Ask your builder which approvals, finance requirements, engineering details or other pre-construction tasks remain, and who is responsible for them.
  • Understand the contract timeframe. Confirm what needs to happen before the construction period starts, rather than assuming it begins on the signing date.
  • Plan communication and inspections. Establish your main contact, how updates will be provided and when independent inspections can be coordinated with the builder.

The exact requirements depend on your contract and project, but these questions provide a useful starting point.

1. What Happens Before Construction Starts?

One of the first things to understand is that signing a building contract and being ready to start construction aren’t necessarily the same thing.

There may still be several requirements to complete.

Final plans and documentation

Your builder needs the necessary plans, specifications and engineering details to construct the home.

These documents should reflect what you’ve agreed to build.

For example, if you’ve moved a window, adjusted a room or changed the kitchen layout, those decisions need to be accurately recorded in the relevant drawings.

The same applies to your selected materials, fixtures and finishes.

I’d recommend making sure you understand which documents represent the final agreed design.

Changes discussed during the planning process shouldn’t be assumed to be included unless they’re properly documented.

Approvals and finance

Most new homes require building approval before construction begins.

Depending on the project, other approvals or conditions may also need to be satisfied.

If you’re using construction finance, your lender may require the signed contract, approved plans, insurance information and other documentation before authorising construction funding.

The requirements will vary between lenders and projects.

What should you ask your builder?

Rather than simply asking when construction will start, I’d recommend asking:

“What exactly still needs to happen before construction can begin, and which items are currently outstanding?”

This gives you a clearer picture of where the project stands.

It’s also worth confirming how your construction period is calculated under the contract.

The date you sign may not be the date the contractual construction timeframe begins.

2. Site Preparation, Footings and Foundations

Once the necessary requirements have been met, construction can begin.

The first activities usually involve preparing the site and establishing where the home will be built.

Site preparation

Depending on the block, this may involve clearing, excavation, levelling, drainage work and preparing access for construction vehicles.

Some blocks require relatively little work.

Others may need substantial excavation, retaining walls or additional engineering.

These requirements should have been considered when developing the home design and overall project budget.

If you’re still working through the planning stage, our article Buying Land to Build a Home in Australia explains why the land, home design and budget need to be considered together.

Setting out the home

Before the foundations are built, the position of the home needs to be established on the block.

This is commonly called setting out.

It’s particularly important when building close to property boundaries or where the site has easements or other restrictions.

Footings and foundations

For homes built on a concrete slab, this stage may involve preparing the footings and beams, installing reinforcement, placing under-slab services and pouring concrete.

Other homes may use different foundation systems.

The construction method should follow the approved engineering design.

An important inspection opportunity

Some foundation components are difficult or impossible to inspect properly once they’re covered by concrete.

That’s why a pre-slab inspection needs to take place at the appropriate time.

A qualified independent inspector can provide an additional assessment of relevant work before it becomes concealed.

This is separate from any required statutory inspection.

One practical point I’d emphasise is that an inspection arranged too late may have limited value.

It’s much better to establish the inspection arrangements before construction begins so the builder knows when access will be required.

3. Frame, Roofing and Lock-Up

This is the stage when your new home starts to become recognisable.

The frame goes up, the shape of the rooms becomes clearer and you can begin to imagine moving through the finished home.

Frame construction

Depending on the design, the frame may be built using timber, steel or other structural materials.

The work can include wall frames, roof trusses, structural members and bracing.

An independent frame inspection provides an opportunity to assess relevant construction details before more of the structure becomes concealed.

Roofing and external construction

As construction progresses, the builder arranges the roofing, external walls, windows and doors.

The exact sequence varies depending on the building system.

For example, a brick veneer home may follow a different sequence from a home using lightweight external cladding.

What is the lock-up stage?

You may hear your builder refer to lock-up.

This generally means the home has reached a defined level of enclosure.

However, the precise requirements for a lock-up progress payment depend on your contract and applicable law.

Don’t assume that every builder uses exactly the same definition.

Why might progress appear to slow down?

During framing, it’s possible to see dramatic changes over a relatively short period.

Later, the work may become less obvious.

Trades could be installing services, completing detailed work or waiting for inspections before proceeding.

A few days without visible changes doesn’t automatically mean there’s a problem.

If you’re concerned, ask your builder for an update on what’s being completed and what comes next.

4. Plumbing, Electrical Work, Insulation and Waterproofing

Once the structure is progressing, attention turns towards many of the components that will eventually be hidden inside the home.

This is a particularly important part of construction.

Plumbing and electrical rough-in

Before internal walls are lined, plumbers and electricians install pipes, wiring and other services.

Depending on the home, this may also include air-conditioning, ventilation, data cabling and other systems.

Their locations need to match the agreed plans and selections.

For example, if you’ve specified extra power points, particular lighting arrangements or changes to plumbing fixtures, the relevant trades need accurate information.

Making those changes after the walls have been lined can be considerably more difficult.

Insulation and internal linings

Insulation and plasterboard are generally installed after the required earlier work and checks have been completed.

Once the plasterboard is fitted, the rooms begin to look much closer to their finished appearance.

However, much of the framing and services are now hidden.

This is why a pre-plaster inspection can be valuable.

It’s an opportunity for a suitably qualified inspector to assess relevant work before it becomes concealed.

Waterproofing

Bathrooms, showers and other wet areas require suitable waterproofing.

This work is particularly important because membranes and other waterproofing components often become concealed behind tiles and finishes.

An independent waterproofing inspection can provide another opportunity to check relevant work before it’s covered.

The timing must be coordinated with the builder and inspection provider because the construction sequence can vary.

Good building work isn’t only about what the finished home looks like. Many of the most important details are things you’ll never see once construction is complete.

For a detailed explanation of inspection stages, see Independent Building Inspections Throughout Your Build.

5. Internal Fit-Out and Finishing Work

Once the internal linings are complete, the home moves towards its finished appearance.

This stage can involve cabinetry, doors, skirting boards, architraves, tiling, painting, flooring and the installation of fixtures.

Different trades may be working in separate areas of the house at the same time.

Check the work against your agreed selections

Your kitchen, bathroom vanities and other cabinetry should reflect the agreed plans and specifications.

It’s worth confirming that the materials, finishes and layouts match what you’ve selected.

The same applies to plumbing fixtures, electrical fittings, tiles and other items.

That doesn’t mean every unfinished surface should look perfect during installation.

Some work will still need adjusting, finishing or cleaning.

But if something appears different from your documented selections, I’d recommend asking about it before more work is completed.

For example, if a cabinet configuration doesn’t match the plan, it may be easier to clarify the issue before the benchtop is installed.

External work

Driveways, paths, fencing, landscaping and other outdoor items may also be completed during this period.

However, not every external item will necessarily be included in your building contract.

The actual scope depends on what you’ve agreed with the builder.

When reviewing your home, compare what’s being built with your contract documents rather than relying on what you remember seeing in a display home.

6. How Do Progress Payments, Variations and Delays Work?

There are several important matters to manage throughout construction.

These aren’t limited to one stage of the build.

Progress payments

Most new home building contracts include payments at agreed construction stages.

Depending on the contract, these might include foundations, frame, lock-up, fixing and completion.

The stage definitions and payment requirements vary.

Before making a payment, understand what the contract says must be completed.

For example, if you receive a frame-stage payment claim, check the contractual definition of that stage.

It’s reasonable to ask your builder to explain the claim if you’re uncertain.

You also need to consider the applicable legal requirements and any conditions imposed by your lender.

A few outstanding items don’t automatically mean a stage hasn’t been reached, but a payment request alone doesn’t establish that the required work has been completed.

If there’s a disagreement, seek appropriate advice before withholding payment.

Variations

A variation is a change to the agreed building work.

It might involve an additional power point, different materials, a window change or a modification to part of the design.

Other variations may arise from unexpected site conditions or engineering requirements.

Before approving a variation, I’d recommend understanding four things:

  • Exactly what is changing.
  • The additional cost or credit.
  • Whether the construction timeframe will change.
  • Whether the change affects any other part of the design.

Variations should be documented and approved in accordance with the contract and applicable law.

A conversation with a tradesperson on site shouldn’t replace the agreed variation process.

Construction delays

Building a home involves many activities that need to happen in the correct sequence.

Weather, supply issues, changes to the design, approvals and unforeseen site conditions can all affect progress.

Not every delay means the builder has done something wrong.

Equally, not every delay automatically gives a builder the right to extend the construction period.

The contract and applicable law determine how extensions of time are managed.

If the completion date changes, ask your builder to explain the reason, the expected effect and how it relates to the contract.

Communication is important

I’d recommend establishing a clear communication process early.

Know who your main contact is, how updates will be provided and how important questions should be raised.

You shouldn’t need to contact your site supervisor constantly to find out what’s happening.

But you should have a reasonable understanding of the project’s progress and any decisions that require your attention.

For important changes or agreements, keep a written record.

A simple email confirming what’s been discussed can help avoid misunderstandings later.

7. What Happens at Practical Completion and Handover?

Eventually, your builder will advise that the home is approaching practical completion.

This is an important milestone, but it’s worth understanding exactly what it means.

What is practical completion?

Practical completion generally means the contracted work has reached the level of completion required under the contract.

Depending on the contractual definition and applicable requirements, some minor defects or outstanding items may be permitted.

That doesn’t mean every unfinished or defective item is acceptable.

The nature of the issue matters.

The practical completion inspection

Before handover, there is generally an opportunity to inspect the home and record relevant concerns.

The builder may arrange a walkthrough with you.

I’d also recommend arranging an independent practical completion inspection.

A qualified inspector can assess relevant workmanship and identify items that may require attention.

Their findings should be considered alongside the contract, applicable building requirements and required certification.

What happens if defects are found?

It’s important to document defects and outstanding work clearly.

Some matters may need to be resolved before practical completion or handover.

Others may be addressed afterwards under the relevant contract arrangements.

If there’s disagreement about whether practical completion has been reached, seek appropriate advice before making decisions that affect your contractual obligations.

Final payment and receiving the keys

Final payment and handover requirements depend on your contract and applicable law.

Before handover, make sure you understand what approvals and documents are required, what payments are due and what outstanding items have been recorded.

Depending on the home, relevant documents may include occupancy or final inspection certificates, warranties, appliance information and other handover records.

Keep these documents somewhere safe.

They may be important for maintenance, warranty matters or future building work.

The defects liability period

Receiving the keys doesn’t necessarily mean the builder’s responsibilities have ended.

Most residential building arrangements include provisions for dealing with defects identified after completion.

There may also be separate statutory warranties and consumer protections.

The applicable timeframes vary depending on the state, contract and nature of the issue.

It’s worth understanding how defects must be reported.

An independent inspection towards the end of the contractual defects liability period can also be useful.

This provides another opportunity to identify relevant issues before that period ends.

What Should You Do If Something Doesn’t Look Right During Construction?

It’s natural to notice things during construction that you don’t fully understand.

Perhaps a window appears to be in the wrong position, a room looks smaller than expected or something seems unfinished.

The first step is to check your plans and specifications.

If you’re still concerned, ask your builder for an explanation.

I’d recommend describing exactly what you’ve noticed rather than immediately assuming the work is defective.

For example, instead of saying a window has been installed incorrectly, you might ask why its position appears different from the approved drawing.

There may be a reasonable explanation.

If the matter involves a technical concern, an independent building inspector or another suitably qualified professional may need to assess it.

I’d also avoid directing tradespeople to change work without going through the builder.

The builder is responsible for coordinating construction, and instructions given outside the agreed process can create confusion about what has been authorised.

Site visits should always follow the applicable access arrangements and safety requirements.

The aim is to identify genuine concerns, understand what’s happening and give everyone an opportunity to resolve issues constructively.

How New Build Assist Can Help Throughout Construction

Building a home involves more than choosing a design and waiting for the keys.

There are important decisions before construction begins, and there are opportunities throughout the build to check the work and clarify any concerns.

That’s why New Build Assist helps clients both before and during construction.

Ideally, the process begins before you’ve committed to a builder.

I help clients work through their home requirements, land, overall budget and suitable builder options.

Once a builder has been selected, I can help clients understand what’s being proposed before they sign the building contract.

During construction, my role is to remain an independent advocate who can help you understand what’s happening and raise questions where necessary.

This can include arranging independent building inspections, helping you understand inspection findings and assisting with communication when matters need to be clarified with the builder.

The inspections are carried out by qualified, independent third-party inspectors.

You receive the inspection reports and pay the inspection company directly.

I don’t replace the builder, the site supervisor, the building certifier or the independent inspector.

The building contract also remains between you and your builder.

The aim is to give you another experienced perspective throughout the building process, without interfering with the builder’s responsibility to construct your home.

The full NBA service depends on working with builders who are willing to cooperate with this approach.

That’s why I encourage people to speak with New Build Assist before establishing direct relationships with builders.

If you’ve already signed a contract, the assistance available may be more limited.

You can learn more about the service on our How New Build Assist Works page.

A Better Place to Start

If you’ve already signed a building contract, the steps in this article can help you prepare questions for your builder, understand what’s still outstanding and discuss whether independent inspections can be arranged during construction.

New Build Assist’s full service is designed to begin before you commit to a builder and depends on builder cooperation. If you’ve already signed, the assistance available may be more limited.

If you’re still looking for land, comparing floor plans or deciding which builders to approach, this is a good time to get clear on the process before making major commitments.

We can begin with a 30-minute conversation about the home you’d like to build, where you’d like to build and your overall budget.

I’ll then prepare a short Personalised Build Plan outlining your priorities, what still needs to be considered and some sensible next steps.

There’s no cost for the initial conversation or the Personalised Build Plan, and no obligation to continue.

Start My Build Plan

No cost. No obligation. Just a better place to start.